Fee schedule
Residential
| Fee category | Amount |
|---|---|
| One-family residence less than 1,600 square feet | $75 |
| All other one-family residences | $115 |
| Residential expansion, including decks and driveways | $40 |
| Multi-family residence — entire building | $210 |
| Accessory building | $40 |
| Special Use Permit — Home Occupation | $100 |
Fee schedule
Non-residential
| Fee category | Amount |
|---|---|
| Site Plan Review | $225 |
| Site Plan Review — Amendment | $150 |
| Special Use Permit | $275 |
| Rezoning | $375 |
| Planned Unit Development | $545 |
| Communication Towers | $500 |
| Accessory building | $75 |
| Addition | $100 |
| Public Buildings | No fee |
| Farming Activities | No fee |
Fee schedule
Signage
| Fee category | Amount |
|---|---|
| Free-standing sign | $50 |
| Sign on building | $40 |
Fee schedule
Zoning Board of Appeals
| Fee category | Amount |
|---|---|
| Application / Review | $275 |
Fee schedule
Special meetings
| Meeting type | Amount |
|---|---|
| Zoning Board of Appeals | $300 |
| Planning Commission | $500 |
Submitting an application
Before work begins
1
Confirm the application
Use the correct current form and include required plans and supporting documents.
2
Confirm the amount
Ask the Zoning Administrator or Township Office which category applies before paying.
3
Wait for the permit
Do not begin construction before issuance; the published schedule doubles all fees when work starts first.
Which fee applies to your project?
Contact the Township Office before submitting payment or beginning work.
The fee schedule was amended at the regular Township Board meeting held March 18, 2025. Confirm the current fee and applicable category with the Township before submitting payment.